회차 · v2020-02-12
A project team member agrees to change a project deliverable after a conversation with an external stakeholder. It is later discovered that the change has had an
adverse effect on another deliverable. This could have been avoided if the project team had implemented:
adverse effect on another deliverable. This could have been avoided if the project team had implemented:
문제 목록·복습
정답오답미응답
시험 기본정보
PMI PMP 자격증 기출문제
PMI PMP