Skip to content
Quizeey
한국어
PMI PMP
Exam set
All
v2020-02-12
Apply
Question
1
/ 1
Set · v2020-02-12
Tools and techniques used for Plan Communications include the communication:
Select one
A
requirements analysis, communication technology, communication models, and communication methods.
B
methods, stakeholder register, communication technology, and communication models.
C
requirements, communication technology, communication requirements analysis, and communication methods.
D
management plan, communication technology, communication models, and communication requirements analysis.
Check answer
Previous
Skip
Questions & review
Correct
Incorrect
Unanswered
1
Review mistakes
0
Review bookmarks
0
Question link
About this exam
PMI PMP pactice questions.