Skip to content
Quizeey
Dark
한국어
PMI PMP
Comments
▶
Exam set
All
2026-10
v2020-02-12
Apply
Question
1
/ 20
Set · v2020-02-12
Plan-do-check-act is also known as:
Select one
A
prevention over inspection.
B
statistical sampling.
C
management responsibility.
D
continuous improvement.
Check answer
Previous
Skip
Questions & review
Correct
Incorrect
Unanswered
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
Review mistakes
0
Review bookmarks
0
Question link
Previous questions
30 / 59
Next questions
About this exam
PMI PMP pactice questions.
Exam comments
PMI PMP