Tools and techniques used for Plan Communications include the communication:
Select one
A
requirements analysis, communication technology, communication models, and communication methods.
B
methods, stakeholder register, communication technology, and communication models.
C
requirements, communication technology, communication requirements analysis, and communication methods.
D
management plan, communication technology, communication models, and communication requirements analysis.